Toyota Tundra Service Manual: Installation

INSTALLATION

PROCEDURE

1. INSTALL GENERATOR ASSEMBLY

(a) Install the generator with the 3 bolts and nut.

Torque:

43 N·m {438 kgf·cm, 32 ft·lbf}

(b) Install the harness bracket to the generator with the bolt.

Torque:

31 N·m {316 kgf·cm, 23 ft·lbf}

(c) Connect the generator connector.

(d) Connect the generator wire with the nut.

Torque:

9.8 N·m {100 kgf·cm, 87 in·lbf}

(e) Install the terminal cap.

2. CONNECT VANE PUMP ASSEMBLY

3. CONNECT POWER STEERING OIL PRESSURE SWITCH CONNECTOR

4. INSTALL FRONT FENDER APRON SEAL RH

5. INSTALL AIR CLEANER ASSEMBLY

6. INSTALL FAN AND GENERATOR V BELT

(a) Install the fan and generator V belt (See page ).

7. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Inspection

    Reassembly

    See More:

    Toyota Tundra Service Manual > Dynamic Radar Cruise Control System: Freeze Frame Data
    FREEZE FRAME DATA CHECK FREEZE FRAME DATA HINT: The ECU records vehicle and driving condition information as freeze frame data the moment a DTC is stored. (a) Connect the Techstream to the DLC3. (b) Turn the ignition switch to ON. (c) Turn the Techstream on. (d) Enter the following menus: Powertrain ...

    Toyota Tundra Owners Manual

    Toyota Tundra Service Manual

    © 2026 Copyright www.ttundra.com
    0.0131