INSTALLATION

PROCEDURE

1. INSTALL GENERATOR ASSEMBLY

(a) Install the generator with the 3 bolts and nut.

Torque:

43 N·m {438 kgf·cm, 32 ft·lbf}

(b) Install the harness bracket to the generator with the bolt.

Torque:

31 N·m {316 kgf·cm, 23 ft·lbf}

(c) Connect the generator connector.

(d) Connect the generator wire with the nut.

Torque:

9.8 N·m {100 kgf·cm, 87 in·lbf}

(e) Install the terminal cap.

2. CONNECT VANE PUMP ASSEMBLY

3. CONNECT POWER STEERING OIL PRESSURE SWITCH CONNECTOR

4. INSTALL FRONT FENDER APRON SEAL RH

5. INSTALL AIR CLEANER ASSEMBLY

6. INSTALL FAN AND GENERATOR V BELT

(a) Install the fan and generator V belt (See page ).

7. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

    Inspection

    Reassembly

    See More:

    Toyota Tundra Service Manual > Clearance Sonar Main Switch: Inspection
    INSPECTION PROCEDURE 1. INSPECT BACK SONAR OR CLEARANCE SONAR SWITCH ASSEMBLY (a) Measure the resistance according to the value(s) in the table below. Standard Resistance: Tester Connection Switch Condition Specified Condition 7 (IG) - 8 (SK) Sonar switch off 10 kΩ or higher Sonar switch on Below 1 ...

    Toyota Tundra Owners Manual

    Toyota Tundra Service Manual

    © 2026 Copyright www.ttundra.com
    0.0125