INSTALLATION PROCEDURE 1. INSTALL STARTER ASSEMBLY (a) Install the flywheel housing side cover. (b) Install the starter with the 2 bolts. Torque: 37 N·m {377 kgf·cm, 27 ft·lbf} (c) Connect the starter wire with the nut. Torque: 9.8 N·m {100 kgf·cm, 87 in·lbf} (d) Connect the starter connector. (e) Attach the 2 wire harness clamps. 2. INSTALL STARTER COVER (a) Install the starter cover with the 3 bolts. Torque: 12 N·m {117 kgf·cm, 8 ft·lbf} 3. INSTALL EXHAUST MANIFOLD SUB-ASSEMBLY RH (See page 4. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL |
Toyota Tundra Service Manual > Air Conditioning: Solar Sensor(for Automatic Air Conditioning System)
Components COMPONENTS ILLUSTRATION Inspection INSPECTION PROCEDURE 1. INSPECT AUTOMATIC LIGHT CONTROL SENSOR (SOLAR SENSOR) (a) Connect the positive (+) lead from the battery to terminal 6 and the negative (-) lead to terminal 3, and then measure the voltage according to the value(s) in the table be ...