INSTALLATION PROCEDURE 1. INSTALL NAVIGATION ANTENNA ASSEMBLY (a) Attach the 2 guides to install the navigation antenna assembly. (b) Install the 2 screws. (c) Attach the 2 clamps. 2. INSTALL DEFROSTER NOZZLE ASSEMBLY
3. INSTALL NO. 1 SIDE DEFROSTER NOZZLE DUCT 4. INSTALL NO. 2 SIDE DEFROSTER NOZZLE DUCT 5. INSTALL NO. 2 HEATER TO REGISTER DUCT 6. INSTALL INSTRUMENT PANEL SUB-ASSEMBLY (a) for Column Shift Type: (See page (b) for Floor Shift Type: (See page
7. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL NOTICE: When disconnecting the cable, some systems need to be initialized after the cable is reconnected (See page
8. CHECK SRS WARNING LIGHT (See page |
Toyota Tundra Service Manual > Cylinder Head: Replacement
REPLACEMENT PROCEDURE 1. REPLACE INTAKE VALVE GUIDE BUSH (a) Heat the cylinder head to approximately 80 to 100°C (176 to 212°F). (b) Place the cylinder head on wooden blocks. (c) Using SST and a hammer, tap out the valve guide bush. SST: 09201-10000 09201-01050 SST: 09950-70010 09951-07100 (d) Usi ...